 93. IDENTIFICATION MARKER OR PLAQUES

   

   

1. SCOPE

The work shall consist of furnishing and installing identification markers or plaques at the designated locations.

2. MATERIALS

The markers or plaques shall be constructed of the specified materials, and shall meet all requirements for lettering, painting, finishing, and related items as shown on the drawings or as specified in Section 6 of this specification.

3. CONSTRUCTION METHODS

The markers or plaques shall be installed at location(s) as shown on the drawings and in the manner or condition specified in Section 6.

4. MONUMENTS

Unless otherwise specified, the markers or plaques shall be mounted on concrete monuments, on existing structures, or on structures proposed for installation under this contract.

5. MEASUREMENT AND PAYMENT

Method 1 For items of work for which specific unit prices are established in the contract, payment for each type, kind, and size of marker or plaque complete in place, will be made at the contract unit price for that type, kind, and size. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 2 For items of work for which specific lump sum prices are established in the contract, payment for identification markers or plaques will be made at the contract lump sum price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

All Methods The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in Section 6 of this specification.