Financial analysis: | |
Environmental impact analysis: | --- |
Waste management/P2: | |
Environmental cost listing/database: | --- |
Cost estimation: | --- |
Alternative product/process comparison: | --- |
Cost control | |
Resource control | --- |
Estimating control | |
Schedule control | --- |
Scope control | --- |
Risk control | --- |
The Parade software is for measuring performance and allows users to track progress against the plan using earned value analysis. It can be used for planning or for period-by-period control. Parade uses WBS (20 levels possible)and OBS (20 levels possible) structures and supports earned value analysis for the project as a whole or for any work element or group. The package has60-year accounting calendars with 12 or 13 month years. Some features of Paradeare as follows:
Parade can consolidate cost data from accounting, schedule data from a scheduler (P3, Finest Hour, and SureTrak Project Scheduler users have special integration features), and also draw estimates from spreadsheet or database files. Thus users have a choice of either building a project in Parade or importing data from elsewhere. Parade can automatically import resource allocations, WBS codes, rate escalations, and resource distribution curves fromP3.
Raw material acquisition | --- |
Manufacturing stage | |
Use/reuse/maintenance | --- |
Recycle/waste management | --- |
The system is not designed to consider more than one life-cycle stage, and it will typically be used to consider the manufacturing stage of the life cycle. Parade uses WBS (20 levels possible) and OBS (20 levels possible) structures, and this is one way that life-cycle information can be entered into the system.
Conventional | |
Potentially hidden | --- |
Contingent | --- |
External | --- |
Cost accounts in Parade can contain detailed, period-by-period task and resource plans. Parade tracks direct labor, material, equipment, travel, and other costs. The analysis data are presented in units, direct costs, or burdened costs. However, flexibility is afforded to users because it is possible to have unlimited resources per task and unlimited tasks and work packages per project. Additional cost categories cannot be created in Parade, and codes cannot be assigned to work packages.
Parade is not designed for project cost estimation. It automatically calculates estimate to complete and latest revised estimate costs for on-going projects.
Net present value (NPV) | --- |
Payback period | --- |
Internal rate of return (IRR) | --- |
Benefits cost ratio | --- |
Other | --- |
Parade can integrate cost and schedule data from a variety of other accounting, cost, and scheduling systems. In a multi-user environment, Parade permits simultaneous updating, reporting, and plotting.
Telephone hotline support and bulletin board. Working demonstration disks are available for Parade, limited by the maximum number of activities (60).
The system does not include all the cost categories. User-defined cost categories cannot be added into the system. Parade is not designed for Life-cycle cost analysis.
Return to the Table of Contents