It is not required to revise a certified plan
to reflect standard changes pursuant to 15A
NCAC 2H. 0217 (a)(1)(H)(xi), but it is encouraged. If a discharge
occurs, or there is documentation that surface waters or groundwaters
has been impacted, then the facility will be required to update
the plan according to the most current technical specifications
or apply for and receive an individual permit.
For each change in farm ownership, the new owner shall submit a
completed Change of Ownership form (Appendix 2.2A) within 60 days
of ownership transfer. The approved plan must be understood, implemented,
signed, and placed within the farm records and on file with the
local SWCD. If the CAWMP is changed, a technical specialist shall
certify the new plan to meet current standards and specifications
for operation and maintenance, and a new certification shall be
submitted to DWQ. Making no changes or only approved cropping changes
to the waste utilization plan does not require a new certification.
A farm operating below threshold or at zero population may be deactivated
from the state's database by submitting a completed Request for
Removal form (Appendix 2.2B) to DWQ. Once a producer submits a removal
request, a site visit will be made by either a regional DWQ, NRCS,
DSWC, or SWCD representative to verify the operation is below threshold
or at zero population, and to determine that no problems exist at
the site. Once this visit occurs that agency will submit a Confirmation
of Removal form (Appendix 2.2C) to DWQ. The operation will retain
its certification or deemed permitted status as allowed by 2H
.0217 as long as there are no existing or projected environmental
impacts. If the Director of DWQ determines at any time that the
facility is the source of existing or projected environmental impacts,
the facility will have to correct the problem(s), is subject to
an enforcement action, and/or is required to apply for an individual
or general permit.
Deactivation does not remove the operation from
the state database but indicates the facility is not subject to
routine compliance inspections and operation reviews, and the waste
does not have to be land applied by a certified animal waste applicator.
For complete removal from the state database, all waste structures
on the farm must be properly closed according to NRCS standards
(see Section 3.1).
Any facilities wishing to reactivate shall implement a certified
animal waste management plan before facility can restock above threshold
numbers. The certified animal waste management plan shall comply
with all Statutes and Rules in effect at the time of certification.
The facility would also be required to apply for and receive coverage
under a general or individual permit before restocking.
For facilities that have been out of operation
for less than four years whether below threshold or no animals on-site
shall submit the following:
- Reactivation Request (Appendix 2.2C)
- Permit Application
- Certification
- Proof of a significant number of animals
on site within the past 4 years for a period of 45 days or more.
- Vet Records
- Kill Dates
- Market Sales for this facility
- OIC Form
For facilities that have been out of operation
for more than four years whether below threshold or no animals on-site
shall submit the following:
- Reactivation Request
- Permit Application
- Certification
- OIC Form
- Lagoon must be brought up to NRCS Standards
Lagoons will be considered new and will have to
meet all current NRCS Standards for lagoons (this includes liner,
sludge storage, and extra 25 year, 24 hour storm event storage.)
If owner exceeds threshold numbers without notifying
DWQ then owner is subject to enforcement action. If work will be
necessary at site the owner may seek approval from DWQ before investing
in the work.
You can submit only documents of when animals
were last on site and request confirmation that DWQ accepts the
submitted documents before submitting permit application and certification.
The downside to not submitting a permit application at the same
time is it will prolong the process. Permit process takes up to
three months and may be longer if any required permit information
is not sent in with the original permit package.
Generally conditional approvals will not be accepted
as part of an operation's certification for a general or individual
permit application. For extenuating circumstances, contact DWQ for
further guidance.
The owner is responsible for obtaining a CAWMP
that has been approved and certified by technical specialists. The
owner shall send the original signed certification form to DWQ.
The owner shall retain a copy. The approved plan shall remain at
the farm site and on file at the local SWCD office.
The owner also shall send a copy of the certification
and the plan to the local SWCD. The district has 30 days to review
the plan for concurrence. If the SWCD concurs with the plan, the
plan is kept on file at the SWCD office. If the SWCD does not concur,
the SWCD will notify in writing the owner, DWQ and DSWC. DWQ will
work with the agricultural agencies to develop an approved plan
or require the owner to apply for and receive an individual permit.
DWQ will acknowledge receipt of all certifications when requested.
The SWCD is required to notify the owner, the
certifying technical specialist, DWQ, and the DSWC if the SWCD does
not concur with the CAWMP. The owner or DWQ may request the SWCD
to reconsider. If the SWCD does not concur, the owner may request
the Soil and Water Conservation Commission (SWCC) to mediate a dispute
over concurrence.
The components for AWMP are listed in Appendix
2.4.
All certifications shall be on the DWQ Animal
Waste Management Certification form (12/05/00). (Appendix 2.5A).
Only a technical specialist who has been designated
under the SWCC rules can certify items on the new form. In order
to sign for an item, the technical specialist must have the corresponding
category of designation (Attachment 2.5B).
Proper calibration of application equipment shall
be documented. The field calibration must show accurate rates of
application. For irrigation equipment, application rates must be
measured at several locations in the application area. For calibration
information see NC Publication Field Calibration Procedures for
Stationary AG-553-1,
Traveler AG-553-2,
and Center Pivots & Linear AG-553-3.
New "non-irrigation" waste application
equipment does not require certification by an irrigation (I) technical
specialist designation under II D, of the CAWMP Certification form.
A WUP may certify manure spreader and honey wagon equipment.
With the requirements of SB 1217, it is very important
to track the dates each part of the certification process was completed.
The certification form was modified to document the date the activity
was completed. The current date should continue to be the date the
form is signed.
If a facility is abandoned or unused for four
years or more, regardless of its certification or permit status,
the farm will be considered a "new" facility for permitting
purposes and the operation would have to meet all permitting requirements
before it could be restocked.
Questions regarding active registration by producers
who depopulated usually involve distinction between "existing"
and "new" systems. 15A NCAC 2H. 0203(21) defines a "new"
animal waste management system as follows:
animal waste management systems which
are constructed and operated at a site where no feedlot existed
previously or where a system serving a feedlot has been abandoned
or unused for a period of four years or more and is then put back
into service. (For purposes of this referenced rule, "abandoned"
and "unused" are interchangeable, meaning ceasing to
exist.)
Therefore, an operation will lose its "existing"
status and be considered a "new" operation if unused for
four or more years. In order to determine the proper categorization
as an "existing" or "new" farm, DWQ uses the
following operating guideline of 10% of the registered number (capacity)
in making this determination, and the rule is being applied as follows:
'Unused' means less than 10% of the registered
number of animals or less than 10% of the number of animals at
system capacity have been on site. Furthermore, consistent with
the EPA definition of an "animal feeding operation",
the requisite number of animals must be shown by the operator
to have been on site for a total 45 days or more within any 12-month
period, or the feedlot will be considered unused for that year.
Any number less than10% is a de minimis attempted
use which would not be generally covered by the spirit or intent
of the rule; however, a producer is allowed to verify to DWQ that
his system had been used in order to retain the operation's "existing"
status.
If an operator needs to verify the farm's "existing"
status or correct his/her registration number in the state database,
he or she must submit a written request to DWQ for the correction
including justification for the change. The producer must also submit
documentation of the existing herd numbers and dates the animals
were housed at the facility as found through market or production
records and/or verification by a government agency official familiar
with the operation. Questions should be directed to Sonya Avant,
the DWQ State Database Coordinator at (919) 733-5083, extension
571, with correction requests submitted to the Division of Water
Quality - Non-Discharge Compliance and Enforcement Group, 1617 Mail
Service Center, Raleigh, NC 27699-1617.
Operations shall not share common sprayfields
and/or waste management systems (other than land application equipment)
unless they are certified and permitted as one operation under the
same ownership.
Effective September 1, 1996 NRCS standards require
irrigation design plans as part of the waste utilization standard
for new and expanding systems. Detailed irrigation plans such as
size of nozzles, operating pressures, etc, shall be part of the
certification process. While this same level of design is not required
for existing systems, the waste utilization standard does require
the waste to be applied uniformly at approved rates and volumes
to prevent runoff. It is the responsibility of the owner to provide
a system to meet these conditions and to verify the availability
of the equipment, land and vegetation.
Even though a technical specialist did not design
the irrigation system, a technical specialist shall certify that
the existing equipment is capable of applying waste to meet requirements
of the CAWMP certification form (Section II D.), and the equipment
is available to use on site (Section III D.).
A producer who does not own waste application
equipment shall contract with a custom applicator to obtain a CAWMP.
If an operation review or compliance inspection
reveals deficiencies in the CAWMP, the operator will be required
to correct the deficiency or complete missing components, change
the plan accordingly, and recertify the operation as needed.
For a facility that cannot currently house its
certified steady state live weight (SSLW), the owner may expand
or construct additional swine houses or a total waste management
system during the moratorium. Under the current moratorium, no additional
housing, lagoons or lagoon expansions can be constructed in Moore
County (see Section
3.2).
A producer may retrofit his or her current waste
management system (i.e./enlarge the current structure, construct
a second stage lagoon, etc.) and have the operation recertified
to a higher number which is NOT to exceed the original registration
number. The operation must first be recertified by a technical specialist,
and the recertification and a request for a permit or COC amendment
shall be submitted to and approved by the DWQ before stocking animals
at the higher recertification number. Under the current moratorium,
no additional housing, lagoons or lagoon expansions can be constructed
in Moore County. (Please refer to Section
3.2).
|