PINK WATER TREATMENT TECHNOLOGY RESEARCH

Revision Date: 6/01
Process Code: Navy/Marines: SR-15-99; Air Force: FA09; Army: N/A
Usage: Navy - Low; Marines - Low; Army - Low; Air Force - Low
Compliance Impact: High
Alternative for: Granular activated carbon (GAC) adsorption systems
Applicable EPCRA Targeted Constituents: Trinitrotoluene (TNT) (Cas 118-96-7), Cyclotrimethylene-Trinitramine (RDX) (Cas 121-82-4), and Cyclotetramethylene-Tetranitramine (HMX) (Cas 2691-41-0)


Overview: The thermophilic biological process (TBP) is used to treat pink water, which is explosive-laden wastewater originating from two munition functions: load, assemble, and pack (LAP) and demilitarization (DEMIL). TBP utilizes granular activated carbon (GAC) to adsorb the explosives from the wastewater, followed by base hydrolysis and thermophilic (microbiological) regeneration of the GAC. The treated wastewater is sent to a wastewater treatment plant. Although additional research is required, the TBP process potentially could be adapted to treat explosives-contaminated groundwater and soils.

TBP is a modification of the Army's present method of GAC regeneration. Currently, Army Ammunition Plants (AAPs) meet pink water discharge requirements by removing the contaminants using GAC adsorption systems. The explosive-laden GAC is either regenerated for reuse or incinerated for disposal. Under the present method, regeneration often does not achieve Army requirements, and the GAC must be disposed as a hazardous waste.

The process begins with the pink water flowing into the GAC adsorption system. The explosive contaminants are first adsorbed onto the GAC, which has demonstrated a high affinity and capacity for these nitrobody compounds. After an adsorption cycle, flow through the GAC column stops and recirculation of a regeneration solution starts. The GAC column is first heated to 80°C (176°F) for base (caustic) hydrolysis, and then cooled to 55°C (131°F) for thermophilic regeneration, inoculated with explosives-degrading organisms, and aerated. The column becomes a bioreactor. Thus, explosive compounds, concentrated by the previous adsorption step, are depleted, and the GAC in the column is regenerated. The bioreactor fluid, containing natural organisms and enzyme systems, passes to the industrial wastewater treatment plant. In the last step, the regenerated GAC column cools and is placed on stand-by.

A TBP pilot-scale plant was installed and operated at the Milan AAP (MLAAP), Milan, Tennessee, prior to being transitioned to the Iowa AAP (IAAAP), Middletown, Iowa, in February 2001. This plant is capable of processing 1.5-2.0 gallons per minute. The TBP skid equipment is self-contained, and consists of three GAC columns, a regeneration tank, pumps, air compressor, a chemical injection system, and instrumentation/controls.

Five confirmatory tests were completed at the MLAAP. Through this demonstration project, the following conclusions were reached:

  1. The thermophilic biological process is technically sound.
  2. Under optimized conditions, this TBP technology degraded over 90% of the nitrobodies from the loaded GAC. During loading, the discharge of nitrobodies from the regenerated GAC in the column gave slightly higher (better) percent removals of nitrobodies compared to that of loading with virgin GAC.
  3. The water discharged is non-toxic, according to results from toxicity testing.
  4. The TBP is economically viable for a full-scale operating system.

Using spent GAC provided by IAAAP, a loading and regenerating cycle of three (3) more tests was complete in March 2001. The results showed a Destruction and Removal Efficiency (DRE) of explosives from the GAC surface of 99.2, 98.4, and 99.2 percent in the three tests, respectively.


Compliance Benefit: Pink water by definition is a Resource Conservation Recovery Act (RCRA) K047 Hazardous Waste due to the presence of nitrobodies, including 2,4,6 trinitrotoluene (TNT), cyclotrimethylene-trinitramine (RDX), and cyclotetramethylene-tetranitramine (HMX). The exact composition of pink water is highly variable and dependent on process materials and operations. The maximum concentration of dissolved energetic-related pollutants, in pink water, is 200 parts per million. Statutes also mandate that pink water be treated prior to disposal.

The U.S. Army required a DRE rate of 80-90 percent or higher. The DRE is the difference in the amount of nitrobodies on the GAC, before and after regeneration, and is reported as a percentage of the total loading of nitrobodies on the GAC. The TBP achieved DRE rates of greater than 90 percent under optimum operating conditions.

The Compliance Benefits listed here are only meant to be used as a general guideline and are not meant to be strictly interpreted. Actual Compliance Benefits will vary depending on the factors involved, e.g., the amount of workload involved.


Materials Compatibility:
No materials compatibility issues were identified.


Safety and Health: The technology itself poses no safety or health risks. However, several contaminants in the pink water are dangerous, and precautions should be taken. Proper personal protective equipment is recommended. The personnel in work areas should wear safety glasses with side-shields and steel-toed safety shoes. Hands should be protected with nitrile (rubber) gloves when loading the column with pink water and when handling the microorganisms. Good hygiene (e.g., washing hands with antibacterial liquid soap after handling the microorganisms) and daily housekeeping should be practiced. Neither respirators nor special ventilation are required.

Consult your local industrial health specialist and your local health and safety personnel prior to implementing this technology.


Benefits:
  • Biodegrades most nitrobodies in explosives-laden wastewater and renders them nontoxic.
  • Regenerates loaded GAC columns, in situ, avoiding the risks and losses associated with handling and incinerating and/or regenerating the spent GAC by combustion.
  • Can be retrofitted to the existing GAC adsorption systems installed at most of the AAPs, with only minor modifications.
  • Requires less energy than other processes currently in use.
  • Commercially available.


Disadvantages:
  • Capital costs may be significant


Economic Analysis: The following cost elements compare the use of a conventional GAC adsorption system using GAC once with a TBP that regenerates the GAC five times.


Assumptions:
  • Costs were calculated from data obtained from pilot-scale test results. The TBP retrofit system was scaled up for a 20-gpm system that loads one carbon bed per week, based on data from the IAAAP. (The pink water treatment systems at the MLAAP operate at 40- to 80-gpm and are currently utilized only sparingly. If the MLAAP was fully operational, and if the pink water treatment system design had specified a flow rate within the 40-80 gpm range, the cost breakdown for MLAAP's estimated treatment cost would be proportionately equivalent to results shown below.)
  • Five regenerations occurred with the TBP technology.
  • Breakdown of the cost categories is shown in the following table.

Table 1. Annual Operating Costs for Pink Water Treatment Technologies

Cost Category

Input
Parameter

Unit
Cost

Baseline

TBP

Labor

changing GAC

$44/hr

$27,456

$4,576

regeneration

---

$15,253

Materials

GAC (new, virgin)

$1.305/lb

$40,716

$6,942

chemicals/microbes

various

---

$9,377

Utilities

electricity

$0.054/kWh

---

$943

steam

$15/1000 lbs.

---

$650

water/sewer

$5/1000 gal

---

$347

Waste Management

waste disposal

$0.50/lb

$31,200

$5,200

drums and liners

$71.10/drum

$22,183

$3,697

reg. compliance

$45/hr

$10,395

$2,295

TOTAL (per year) using new, virgin GAC

$131,950

$49,285

Capital Cost: The capital cost to retrofit the TBP technology to an existing 20-gpm system is approximately $230,560.


Operational Cost: Operating costs for GAC TBP will vary considerable depending upon the process configuration required for the particular GAC regeneration application. Annual operating costs for the field-level GAC TBP system were estimated at $49,285, versus $131,950 per year for a conventional GAC process.


Payback Period: The calculated payback period for investment in the equipment/process is 3.44 years, using a 15-year analysis, 10% discount rate, and a straight line depreciation over a period of 10 years.


Annual Savings: The calculated annual saving is $82,665 in operating costs, if the TBP is retrofitted to an existing 20-gpm GAC adsorption system.


Economic Analysis Summary:

A summary of the financial implications for retrofitting a GAC TBP system on a conventional GAC process in field-level activities, which includes annual operating cost benefit and capital investment required, is shown in Table 2. The 15-year NPV and IRR, as well as the payback period are also listed in Table 2.

Table 2: Financial Implications of Retrofitting a Conventional GAC Process with a GAC TBP

Category

Financial Analysis Results

GAC TBP

Conventional GAC

Annual Operating Cost Benefit (per year)

$49,285

$131,950

Investment Required

$230,560 b

$0

Discounted Payback Period (year) a

3.44 years

N/A

NPV a

$400,000

N/A

IRR a

35.5%

N/A

a This value was calculated with Pollution Prevention Financial Analysis and Cost Evaluation System (P2/FINANCE). This software is proprietary and copyrighted by Tellus Institute of Boston, Massachusetts. A 15-year analysis, 10% discount rate were assumed, and a straight-line depreciation over 10 years.
b This number is based on the cost of the equipment, installation, and other fabrication costs. contributing one-time fees related to the process.


NSNs: None Identified.


Approving Authority: Approval is controlled locally, and the technology should be implemented only after engineering approval has been granted. Major claimant approval is not required.


Points of Contact: Dr. Mahmood A. Qazi, Concurrent Technologies Corporation, 100 CTC Drive, Johnstown, PA 15904, Phone: (814) 269-2726


Vendors:

CTC is the sole source of the Thermophilic Biological Process (TBP) Technology.
Concurrent Technologies Corporation
100 CTC Drive, Johnstown, PA 15904
POC: Mahmood A. Qazi, Ph.D
Phone: (814) 269-2726
Fax: (814) 269-6847

This is a complete list, as there are no other suppliers of this type of equipment.

 

Source(s): Concurrent Technologies Corporation. Pilot-Scale Thermophilic (Biological) Process Final Technical Report. June 15, 2000.
Supplement(s) to the Data Sheet:
  • Schematic of the GAC Thermophilic Biological Process (TBP) Pilot Plant
  • Picture of the TBP Pilot Plant Equipment.


[Back]