WET DETENTION PONDS TO TREAT STORM WATER RUNOFF
![]() |
|
Overview: |
A wet detention pond is a
constructed storm water retention pool wherein physical, biological, and
chemical processes remove pollutants from storm water runoff. Pollutants
removed include suspended solids, organic matter, dissolved metals, and
nutrients. In addition, wet detention ponds control storm water flow which
prevents downstream flooding. As storm water enters the pond, treated
water is displaced and discharged into a receiving body of water. Enhanced
treatment of storm water runoff can be achieved through extended detention
and the use of aquatic plants on the perimeter of the pond. Sediment
removal can also be increased through the use of a sediment
forebay. Pollutant removal in the pond is
achieved through one of two methods: solids settling or eutrophication.
The solids settling method relies on pollutant removal through
sedimentation. The eutrophication method removes nutrients using natural
biological processes. According to the National Urban Runoff Program
(NURP), up to 2/3 of the suspended sediments, trace metals, and
nutrients settle out within 24 hours. Other studies, examining biological
removal, suggest hydraulic residence times (HRTs) of close to 2 weeks are
required for phosphorus removal.
Two ratios are useful for predicting pollutant
removal efficiencies: volume ratio and area ratio. Volume ratio (VB/VR) is
the ratio of permanent pool storage (VB) to the mean storm runoff (VR).
Area ratio (A/As) is the ratio of the contributing drainage area (A) to
the permanent pool surface area (As). Both of these ratios are correlated
with treatment efficiencies. Large volume ratios result in increased
retention and treatment between storms, while low pollutant efficiencies
are achieved with low volume ratios.
Sediments collected by the wet detention pond
typically meet toxicity limits and can be landfilled safely. Testing of
the sediments may be required if the upstream drainage area is industrial
and/or results in highly contaminated runoff. Non-toxic sediments can also
be disposed on site, but away from the shoreline to prevent their re-entry
into the pond. The removal of sediments in a pond may be necessary every
20 years. This may be decreased to every 50 years if a sediment forebay is
used prior to the wet pond. The sediment forebay would require maintenance
every 5 to 7 years or when 50% of forebay capacity is
silted.
| |||||||||||||||||||||||||||
Compliance Benefit: | The use of
wet detention ponds for treating storm water runoff may help facilities
meet requirements for implementation of storm water runoff best management
practices contained in stormwater permits and plans (40 CFR
122.26).
The compliance benefits listed here are only meant to be used as a general guideline and are not meant to be strictly interpreted. Actual compliance benefits will vary depending on the factors involved, e.g. the amount of workload involved. | |||||||||||||||||||||||||||
Materials Compatibility: | No materials compatibility issues were identified. | |||||||||||||||||||||||||||
Safety and Health: | Proper
design, operation, and maintenance of the equipment is required for its
safe use. Consult your local Industrial Health specialist, your local
health and safety personnel, and the appropriate MSDS prior to
implementing any of these technologies.
| |||||||||||||||||||||||||||
Benefits: |
| |||||||||||||||||||||||||||
Disadvantages: |
| |||||||||||||||||||||||||||
Economic Analysis: | Budgeting
for construction of a wet detention pond should include costs for
permitting, designing, constructing, and maintaining the pond. Costs will
vary for permitting from state to state, as will requirements concerning
pond construction in a developing area versus a developed one. Developing
areas tend to be less costly, as there are fewer problems presented by
existing utility and other constraints. A publication review indicated an
average cost for a 1acre, 5 foot deep pond with a storage volume of
180,000 cubic feet is $75,000. Fort Meade installed five storm water wet detention ponds in 1997. The cost of the ponds ranged from $4 -7 million. The average pond size is approximately two acres with a depth of one foot. Literature indicates that annual maintenance and operational costs typically range between 3 to 5 percent of construction costs. Maintenance costs include sediment removal, grass mowing, nuisance control (problematic animals), trash removal, and routine inspections. On-site sediment disposal should be utilized when possible, as costs can be reduced by as much as 50 percent. The operation and maintenance costs at Fort Meade are estimated to be less than 1 percent of the total construction costs. Assumptions:
Annual Operating Cost Comparison for Wet Ponds and Sand Filter
Economic Analysis Summary Annual Savings for Wet Detention Pond:
-$215 Based on the above analysis it appears that the operational cost of a sand filter system is similar to that of a wet pond system. However, a wet pond system has a high land requirement. Where land is available, wet pond systems may be more appropriate. Click Here to view an Active Spreadsheet for this Economic Analysis and Enter Your Own Values. To return from the Active Spreadsheet, click the reverse arrow in the Tool Bar. | |||||||||||||||||||||||||||
Approving Authority: | Approval
is controlled locally and should be implemented only after engineering
approval has been granted. Major claimant approval is not
required.
|
NSN/MSDS: |
|
Points of Contact: | Army: Mr. Bill Harmeyer DPW-EMO 239 Ross Street Fort Meade, MD 20755-5115 Phone: (301) 677-9168 FAX: (301) 677-9001 DSN: 622-9168 Email: harmeyerw@emh1.ftmeade.army.mil Civilian: |
Vendors: | Contact local construction or
A&E firms for more information. |
Sources: | Mr. Bill Harmeyer,
Fort Meade, Maryland, January 1999. Hartigan, J. P. 1988. "Basis for Design of Wet Detention Basin BMPs" in Design of Urban Runoff Quality Control. American Society of Engineers. Maryland, Department of Environment (MD), 1986. Feasibility and Design of Wet Ponds to Achieve Water Quality Control. Sediment and Stormwater Administration. Northern Virginia Planning District Commission (NVPDC) and Engineers and Surveyors Institute, 1992. Northern Virginia BMP Handbook. Schueler, T. R, 1992. A Current Assessment of Urban Best Management Practices. Metropolitan Washington Council of Governments. Southeastern Wisconsin Regional Planning Commission (SEWPRC), 1991. Costs for Urban Nonpoint Source Water Pollution Control Measures. Technical Report No. 31. Urbonas, Ben and Peter Stahre, 1993. Stormwater Best Management Practices and Detention for Water Quality, Drainage, and CSO Management. PTR Prentice Hall, Englewood Cliffs, New Jersey. Joint Services Pollution Prevention Technical Library Fact Sheet, Sand Filter for Treating Storm Water Runoff, June 1997. Maryland Department of the Environment, http://www.mde.state.md.us. |
[Back]