Waste Minimization Assessment for a Manufacturer of Aluminum Extrusions

United States Environmental Protection Agency
Research and Development
Risk Reduction Engineering Laboratory
Cincinnati OH 45268

EPA600/S-92/010
April 1992

EPA Environmental Research Brief

F. William Kirsch and Gwen P. Looby'

Abstract

The U.S. Environmental Protection Agency (EPA) has funded a pilot project to assist small- and medium-size manufacturers who want to minimize their generation of hazardous waste but who lack the expertise to do so. Waste Minimization Assessment Centers (WMACs) were established at selected universities and procedures were adapted from the EPA Waste Minimization Opportunity Assessment Manual (EPA/625/7-88/003, July 1988). The WMAC team at the University of Louisville performed an assessment at a plant manufacturing aluminum extrusions - over 10 million lb/yr. Aluminum parts are extruded and tempered followed by electrostatic painting, anodizing, or shipping. The team's report, detailing findings and recommendations, indicated that the most waste was generated by the painting process and that the greatest savings could be obtained by replacing the currently used paints with electrostatic powder coatings.

This Research Brief was developed by the principal investigators and EPA's Risk Reduction Engineering Laboratory, Cincinnati, OH, to announce key findings of an ongoing research project that is fully documented in a separate report of the same file available from the authors.

Introduction

The amount of hazardous waste generated by industrial plants has become an increasingly costly problem for manufacturers and an additional stress on the environment. One solution to the problem of hazardous waste is to reduce or eliminate the waste at its source.

Uriversity City Science Center, Philadelphia, PA 19104

University City Science Center (Philadelphia, PA) has begun a pilot project to assist small- and medium-size manufacturers who want to minimize their formation of hazardous waste but who lack the in-house expertise to do so. Under agreement with EPA's Risk Reduction Engineering Laboratory, the Science Center has established three WMACs. This assessment was done by engineering faculty and students at the University of Louisville's WMAC. The assessment teams have considerable direct experience with process operations in manufacturing plants and also have the knowledge and skills needed to minimize hazardous waste generation.

The waste minimization assessments are done for small- and medium-size manufacturers at no out-of-pocket cost to the client. To qualify for the assessment, each client must fall within Standard Industrial Classification Code 20-39, have gross annual sales not exceeding $50 million, employ no more than 500 persons, and lack in-house expertise in waste minimization.

The potential benefits of the pilot project include minimization of the amount of waste generated by manufacturers, reduced waste treatment and disposal costs for participating plants, valuable experience for graduate and undergraduate students who participate in the program, and a cleaner environment without more regulations and higher costs for manufacturers.

Methodology of Assessments

The waste minimization assessments require several site visits to each client served. In general, the WMACs follow the procedures outlined in the EPA Waste Minimization Opportunity Assessment Manual (EPA/625/7-88/003, July 1988). The WMAC staff locates the sources of hazardous waste in the plant and identifies the current disposal or treatment methods and their associated costs. They then identify and analyze a variety of ways to reduce or eliminate the waste. Specific measures to achieve that goal are recommended and the essential supporting technological and economic information is developed. Finally, a confidential report that details the WMAC's findings and recommendations (including cost savings, implementation costs, and payback times) is prepared for each client.

Printed on Recycled Paper

Plant Background

This plant manufactures painted, anodized, and mill-finished aluminum extrusions. Over 10 million lb of aluminum extrusions are produced each year by the plant's 100 employees who operate the plant approximately 4000 hr/yr.

Manufacturing Process

The manufacturing processes of this plant and the wastes generated are described below.

Extrusion

Three extrusion presses are used to produce aluminum parts. Aluminum billets are processed in two of the presses. First, the billets are coated with an extrusion compound to reduce friction and heated lo 900'F in a furnace. Then the billets are extruded through the appropriate die and the ends of the billets are cut off. The resulting parts are then moved to a cooling station prior to age-hardening.

Aluminum logs are processed in the third press, which is computer-controlled. These logs are also coated and heated to 900'F prior to extrusion. The logs are extruded and cut to size as determined by the control system. The resulting parts are cooled before age-hardening.

The cooled, extruded parts are tempered in ovens at 365'F for 4 hr (age-hardening). The parts are then sent to painting, anodizing, or directly to shipping.

Several wastes are generated by the extrusion process. Aluminum shavings and billet ends are recycled by a sister plant. The caustic solution that is used to clean the extrusion dies is sent to the on-site wastewater treatment plant, Waste hydraulic fluid from the presses is recycled on-site; sludge from the recycler is landfilled. Wastewater from the cooling of the extrusion presses is disposed of through a storm sewer drain.

Painting

Parts that require painting are hung on an overhead conveyor. Prior to painting, the parts are run through a conversion coating system in which a coat of chromium phosphate is bonded to part surfaces for corrosion protection. Parts are dried in a 250'F oven.

After drying, the parts are electrostatically painted in one of two paint booths. Paint is cured in a 350'F oven. Selected parts are then tested. Most of the failed parts are scrapped, but some tailed parts are reworked.

Waste generated by the painting process includes wastewater from the conversion coating process that is sent to the onsite wastewater treatment plant. Chromate chips that result from the cleaning of the solution mixing tank are disposed of in a hazardous waste landfill. A significant amount of overspray paint waste is disposed of in a nonhazardous landfill. Sludge containing xylene and paint results from the cleaning of the paint atomizer parts and is disposed of as a hazardous waste. Hydraulic oil that leaks from the atomizers mixes with paint and xylene in the paint booths and is disposed of in a nonhazardous waste landfill. Used filters from the booths are disposed of in the dumpster with other miscellaneous trash.

Anodizing

Parts to be anodized are degreased, rinsed, etched, rinsed again, and then dipped into the anodizing tank. After anodizing, the parts are rinsed and dipped in a seal tank. Waste solutions from the anodizing line are sent to the onsite WWTP.

Thermalfilling

Painted and anodized parts which will be used in household windows and doors are sent to the thermalfill line. In this process, the cavity of the part is filled with epoxy. Once the parts have dried, a portion of the metal and epoxy is removed to create a discontinuity, thereby providing greater insulation potential.

Waste epoxy resin, aluminum and epoxy cuttings, and waste methylene chloride, which is used to clean the epoxy discharge nozzles, are disposed of in the dumpster.

Existing Waste Management Practices

This plant has already taken the following steps to manage and minimize its wastes:

Waste Minimization Opportunities

The waste streams currently generated by the plant, the waste management methods applied, the quantities of waste, and the annual treatment and disposal costs are given in Table 1.

Table 2 shows the opportunities for waste minimization that the WMAC team recommended for the plant. Current plant practice, the proposed action, and waste reduction, savings, and implementation cost data are given for each opportunity. The quantities of waste currently generated by the plant and possible waste reduction depend on the production level of the plant. All values should be considered in that context.

It should be noted that the economic savings of the minimization opportunity, in most cases, results from the need for less raw material and from reduced present and future costs associated with waste treatment and disposal. Other savings not quantifiable by this study include a wide variety of possible future costs related to changing emissions standards, liability, and employee health. It should also be noted that the savings given for each opportunity reflect the savings achievable when implementing each waste minimization opportunity independently and do not reflect duplication of savings that would result when the opportunities are implemented in a package.

Additional Recommendations

In addition to the opportunities analyzed and recommended by the WMAC, several other possibilities for waste minimization were evaluated by the assessment team. These measures were not completely analyzed because of insufficient data or minimal savings. They were brought to the manufacturer's attention for future reference, however, since these approaches to waste minimization may increase in attractiveness with changing plant conditions.

Table 1. Summary of Current Waste Generation

Waste Stream Generated Waste Management Method Annual Quantity Generated Annual Waste Management Cost
Extrusion
Hydraulic oil sludge Off-site landfill 5,400 lb $4,210
Caustic cleaning solution Treated onsite and sewered 57,600 gal 180
Cooling water from well Storm drain 68,160,000 gal 0
Aluminum shavings and cuttings Recycled by sister plant    
Painting
Paint overspray Off-site landfill 3,300 gal 13,680
Paint and xylene sludge Off-site hazardous waste disposal facility 55 gal 360
Hydraulic oil and paint sludge Off-site landfill 495 gal 1,170
Chromate conversion solutons Treated onsite and sewered 3,720,000 gal 11,840
Chromium chips Off-site hazardous waste disposal facility 1,200 lb 920
Anodizing
Anodizing solutions Treated onsite and sewered 3,732,000 gal 15,040
Thermalfill
Aluminum and epoxy cuttings Dumpster 42, 000 lb 1,370
Epoxy resin and methylene chloride Dumpster 15,000 lb 460
Wastewater Treatment
Chromate sludge Off-site landfill 33,830 gal 13,700
Miscellaneous
Metal packing bands Sold to recycler 18,000 lb (340)'1'
Empty drums Sold to recycler 220 units (220)'1
Paper, cardboard, rags, etc. Dumpster 1,040 Yd'1 450

Quantity and cost not available

Revenue received

This research brief summarizes a part of the work done under Cooperative Agreement No. CR-814903 by the University City Science Center under the sponsorship of the U.S. Environmental Protection Agency. The EPA Project Officer was Emma Lou George.

*U.S. GOVERNMENT PRINTING: 1992 - 648-080/40255

Table 2. Summary of Recommended Waste Minimization Opportunities

Present Ptactice

United States Environmental Protection Agency
Official Business
Penalty for Private Use $300

EPA/600/S-92/010

Proposed Action

Center for Environmental Research Information
Cincinnati, OH 45268

Waste Reduction and Associated Savings

Waste reduction - 2,700 lb/yr
Waste management cost savings - $3,540/yr
Implementation cost - 0
Payback is immediate,

Waste reduction - 1,650 gal/yr
Waste management cost savings - $6,840/yr
Raw material cost savings - $1,800/yr
Total cost savings - $8,640/yr
Implementation cost - $7,500
Simple payback - 0.9 yr

Waste reduction - 2,915 gal/yr
Waste management cost savings - $11,330/yr
Paw material cost savings - $12,600/yr
Total cost savings - $23,930/yr

Implementation cost - $118,000 Simple payback - 5.1 yr
Waste reduction - 5.520,000 gal/yr
Waste management cost savings - $6,790/yr
Water cost savings - $4,750/yr
Operating cost - $580/yr
Not cost savings - $10,96O/yr
Implementation cost - $1,520
Simple payback - 0.2 yr

Waste reduction - 248,000 gal/yr
Waste management cost savings - $500/yr
Raw material cost savings - $5,250/yr
Total cost savings - $5,750/yr
Implementation cost - $35,000
Simple payback - 6.1 yr

Waste reduction - 21,000 lb/yr
Waste management cost savings - $685/yr
Revenue received - $2,940/yr

Total cost savings - $3,625/yr
Implementation cost - $6,180
Simple payback - 1.7 yr

BULK RATE
POSTAGE & FEES PAID
EPA
PERMIT NO. G-35


Last Updated: February 12, 1996