# 2 in a series of 10 case studies

Tidyman's Grocery
Spokane, WA


Photo of Tidyman's Grocery




How specifications were used to reduce construction waste




When the project went out to bid, each subcontractor was required to include a line item for disposal costs. This amount was subtracted from the final bid and an independent waste manager was hired to handle all waste recycling and disposal. The waste managers set up recycling containers and met with subcontractors at their weekly safety meetings to discuss problems and report progress toward recycling goals. The waste manager also posted regular updates on the amount of material recycled so all employees could see the results of their efforts. Waste management costs were 56% less than they would have been with the original bids

Project Description

New construction of
Grocery store;
private sector


Building Size

47,000 square feet


Project Status at Time of Publication

Project complete


Waste Impact

Recycled 48 tons of
Construction waste


Project Costs

reduced
stayed the same
increased


Local Landfill Fee

$57/ton


Contact

John McKinnon
Aztech Environmental
2522 W. Lacrosse
Spokane, WA 99205
505-324-8605


Mike Bolme
Tidyman's Inc.
17515 E. Appleway
Green Acres, WA 99016
509-891-0306